PMP 易错题汇总(二)

A project is falling behind schedule due to several quality issues that request extensive rework. The project manager’s initial review reveals that design changes were the major cause of this rework. What should the project manager do next?
A.Review the quality management plan to ensure that it has ;been updated in line with the change log.
B.Ask stakeholders to stop all change requests until the current quality issues are resolved.
C.Instruct the quality manager to present the design changes to the project team as soon as possible.
D.Defer any new design change requests until the current rework has been resolved.

由于一些需要大量返工的质量问题,一个项目落后于进度。项目经理的初步审查表明,设计变更是这次返工的主要原因,项目经理下一步应该做什么?
 

问题1选项

 A.审核质量管理计划以确保己更新该计划,与变更日志保持一致。

 B.要求相关方在当前质量问题得到解决之前停止所有变更请求。

 C.指示质量经理尽快向项目团队展示设计变更。

 D.推迟任何新的设计变更请求,直到解决当前的返工问题为止。

参考答案: A

设计变更是这次返工的主要原因,变更后没有更新计划,没有通知相关方导致了返工的问题。那么项目经理应该解决这个问题,应该要审核更新计划,选项A正确。
选项B停止所有变更不能从源头解决问题。
选项C和D都不是正确的处理方式


 

 

上一篇:Validate至少有一个不能为空


下一篇:paper 5: KDD2021-Sliding Spectrum Decomposition for Diversified Recommendation